Chilean state-owned copper giant Codelco has secured environmental approval for an $868-million project to extend operations at its Gabriela Mistral mine until 2055, supporting efforts to reverse years of declining production.
The Environmental Assessment Commission (Coeva) in northern Chile’s Antofagasta region unanimously approved the project’s environmental impact study on Monday, Chilean newspaper La Tercera reported.
The plan would extend mining operations by 28 years, from 2028 through 2055, while maintaining copper cathode production capacity at roughly current levels.
The decision marks a step forward for Codelco, which is struggling to rebuild output following historic production lows in 2022 and 2023. Delays to major development projects and operational setbacks have complicated the recovery.
The approval also provides a path to prolong production at the Gabriela Mistral mine, which began operating in 2008 with an initial productive life of 15 years. The open-pit operation is located in Chile’s copper-rich Antofagasta region.
Water transition
The project, formally called Operational Continuity and Water Transition Gabriela Mistral Mining Project, was submitted for environmental review in December 2024. It includes changes to water sourcing and mineral processing intended to support the mine’s long-term operations.
Under the proposal, Codelco would transition to alternative water sources beginning in the ninth year of the project, replacing supplies from the division’s existing registered groundwater extraction wells under normal operating conditions.
The company also plans to introduce sodium chloride into the processing of leachable minerals starting in 2035, a change to the operation’s existing treatment methods.
The project has an overall lifespan of 30 years, including development and operational phases. Construction would require an average workforce of 230 people, with staffing expected to reach 1,200 during operations.
Approval challenges
Although Coeva’s unanimous vote clears a major regulatory hurdle, the project could still face administrative or legal challenges.
Opponents may seek a review by Chile’s Committee of Ministers or pursue appeals through the environmental courts and ultimately the Supreme Court, according to La Tercera. Such proceedings could delay implementation despite the favourable environmental decision.
The approval grants the project a favourable Environmental Qualification Resolution (RCA), although the formal resolution was not immediately available following this week’s vote.