Chile’s environmental regulator has accused state-owned copper giant Codelco of two serious dust-control violations at its Ministro Hales mine, exposing the operation to fines, closure or the loss of its environmental permit.
The Superintendencia del Medio Ambiente (SMA) filed the charges on Thursday following inspections and seven public complaints submitted between 2021 and 2024 in Calama, a northern Chilean city officially designated as saturated with respirable particulate matter known as PM10. Each charge carries a potential fine of up to about $4.3 million, bringing Codelco’s combined exposure to approximately $8.7 million.
“Calama is an area declared saturated with respirable particulate matter, so strict compliance with emissions-control measures is essential to protect public health,” environmental superintendent Emanuel Ibarra said in a statement.
The enforcement action raises fresh regulatory concerns for Codelco, months after Ministro Hales secured final environmental approval for a $2.8-billion project to extend its operating life. The allegations also put Chile’s enforcement of environmental standards at state-owned mining operations under scrutiny.
Dust control failures
The SMA alleges that Codelco operated the mine’s primary crusher without the baghouse filtration system required under its environmental approvals. The regulator also found that dust-removal efficiency fell below the mandated 75% between November 2023 and February 2024.
At the mine’s waste-rock dump, Codelco allegedly failed to apply bischofite, a magnesium chloride-based dust suppressant, to inactive areas during 2023 and 2024. The treatment was intended to reduce wind erosion by 85%.
The regulator also cited missing records documenting implementation of the dust-control measures between 2023 and 2025.
Both alleged breaches were classified as serious under Chilean environmental law. The charges are not final findings of wrongdoing, and any sanctions will depend on the outcome of the proceedings.
The case centres on measures intended to limit airborne dust in a city already struggling with particulate pollution. Failure to maintain those controls could undermine efforts to reduce emissions from mining activity near populated areas.
Tailings compliance
In a separate decision, the SMA approved a compliance program submitted by Codelco to address groundwater infiltration and tailings-management violations at the Talabre tailings facility.
The regulator had filed charges in August 2024 after finding that the company failed to implement a contingency plan in response to changes in groundwater conditions and deposited tailings with a solids content below the required 60%.
The approved program includes eight measures to be implemented over 24 months at an estimated cost of $66.9 billion Chilean pesos ($66.8 million).
Among the principal commitments, Codelco will install 22 additional extraction wells to strengthen the facility’s hydraulic containment barrier, supported by 17 monitoring wells.
The company will also implement its PRECLA tailings preclassification project to achieve the required solids concentration and conduct water-capture tests within the tailings basin.
Approval of the program suspends the earlier enforcement proceedings while Codelco carries out the agreed measures. If the company fails to meet its commitments, the SMA can reopen the case and impose fines of up to twice the original amount.
The two decisions leave Codelco facing separate regulatory obligations at Ministro Hales: defending itself against new allegations involving airborne emissions while completing a costly remediation program addressing tailings and groundwater risks.